Fiber Build Schedule
Check and see when fiber is in your area!. The dates below are estimates of when Make-Ready Construction crews are in your area pulling fiber to your substation! Check out the graphic below the build estimate table to get a better idea of when service may be available to you.
Chiefland 1
Service Now Available
Trenton
Service Now Available
Bell
October 2023
Dempsey
December 2023
Country Club
December 2023
Old Town
1st Quarter 2024
Bronson
1st Quarter 2024
Cross City
2nd Quarter 2024
Williston
2nd Quarter 2024
Newberry
3rd Quarter 2024
Neals
3rd Quarter 2024
Usher
4th Quarter 2024
Renfroe
4th Quarter 2024
Inglis
1st Quarter 2025
Cedar Key
1st Quarter 2025
Town of Suwannee
1st Quarter 2025